2024 Street Maintenance

Bid/RFP Status: 
Awarded
Bid/RFP Due Date: 
Tuesday, May 21, 2024 - 2:00pm
Quest CDN Reference Number: 
9100489

Project consists of furnishing all materials, labor, equipment, and supervision for repaving SW Boones Ferry Road, SW Wilsonville Road to SW Bailey Street, reconstructing SW Boberg Road, SW Boeckman Road to SW Barber Street, repaving SW Bailey Street, SW Boones Ferry Road east to cul-de-sac, roadway repair in select locations, new RRFB, signal modifications, and ADA curb ramps. The improvements consist of approximately 8,600 SY of 0-2 inch cold plane pavement removal, 2,000 SY of 3-inch cold plane pavement removal, 2,300 CY of asphalt and base rock excavation, and 15 new curb ramps. There will be approximately 6,300 tons of asphalt concrete pavement, 230 tons of portland cement, and 100 CY of aggregate base. Performance of such additional and incidental work as called for by the Specifications and Contract Documents.

Bidders must be qualified by the City of Wilsonville (“City”) in compliance with ORS 279C.375(3). Bidders (or their sub-contractors) must also be pre-qualified in compliance with Oregon Revised Statutes Chapter 279C.430 by the Oregon Department of Transportation in the Class of Work “ACP”, “MHA”, “ELEC” and “PAVE” prior to the date bids are due. Bids submitted by a Bidder who is not prequalified prior to the date bids are due will be rejected as non-responsive. In determining the responsiveness and responsibility of any bid submitted, establishing requisite qualification with the City shall not be considered an informality.

Specifications and Contract Documents are available on April 29, 2024 through QuestCDN - www.questcdn.com and input 9100489.

Final Bid Results:

  • Knife River Corporation - $1,760,101.50 
  • Brix Paving Northwest - $1,931,078.50
  • S2 Contractors - $2,462,953.40
  • Kodiak Pacific Construction - $2,762,935.00